Office Design Blogs: Workplace Strategy & Trends UK

Fit-Out Jargon Explained: A Glossary of Fit-Out Acronyms

Written by Candace Fowles | Nov 27, 2026, 10:52:37 AM

Fit-out jargon is the set of acronyms that appear in leases, contracts and drawings for a commercial fit-out, from Heads of Terms (HoTs) at the start of a lease to Operation and Maintenance (O&M) manuals at handover. Habit Action, a UK design-and-build fit-out company working on offices, laboratories, manufacturing and defence spaces, put this glossary together so occupiers can read their own project documents without a translator.

Each term below follows the same layout: what the acronym stands for, what it means, the detail and why it is important, then a short summary. The terms run in the order you usually meet them on a project, starting with the lease and finishing at handover.

Fit-Out Acronyms at a Glance

Find the stage your project is at, then click a term to jump straight to it.

Stage

Acronym

Stands for

In one line

Project stages

RIBA Stage

Royal Institute of British Architects stage

How far a design has progressed, from Stage 0 to Stage 7

Leasing

HoTs

Heads of Terms

The agreed outline of a deal before the lease is drafted

Leasing

LTA

Licence to Alter

The landlord's written consent to your fit-out works

Leasing

Dilaps

Dilapidations

What you owe the landlord for the building's condition when you leave

Contracts

LOI

Letter of Intent

A letter that lets work start before the main contract is signed

Contracts

PCSA

Pre-Construction Services Agreement

A paid agreement for design and pricing before the build contract

Contracts

JCT

Joint Contracts Tribunal

The body behind the UK's most widely used building contracts

Contracts

D&B

Design and Build

One contractor responsible for both design and construction

Space categories

Cat A

Category A

A landlord's base fit-out, finished but empty

Space categories

Cat B

Category B

The occupier's own fit-out, ready to work in

Building services

MEP

Mechanical, Electrical and Plumbing

The building services that make a space usable

Building services

HVAC

Heating, Ventilation and Air Conditioning

The systems that control temperature and air quality

Building services

AHU

Air Handling Unit

The plant that supplies fresh, filtered air

Building services

FCU

Fan Coil Unit

A local unit that heats or cools one zone

Building services

VRF

Variable Refrigerant Flow

A multi-zone heating and cooling system run on refrigerant

Building services

BMS

Building Management System

The control system that runs and monitors building services

Fire safety

FD30, FD60, FD120

Fire Door

The British rating for how many minutes a door resists fire

Fire safety

E30, E60, E120

Integrity

The European integrity-only fire rating for doorsets

Fire safety

EI30, EI60, EI120

Integrity and Insulation

The European fire rating covering integrity and insulation

Site and handover

CDM

Construction (Design and Management) Regulations

The UK law on health and safety in construction projects

Site and handover

FF&E

Furniture, Fixtures and Equipment

The loose and fitted items that complete a space

Site and handover

PC

Practical Completion

The point the works are finished enough to hand over

Site and handover

O&M

Operation and Maintenance

The manuals that tell you how to run what was installed

Site and handover

SKA

SKA rating

The RICS environmental assessment designed for fit-outs

Project Stages

RIBA Stage

What It Stands For

Royal Institute of British Architects stage, referring to a stage of the RIBA Plan of Work.

What It Means

The RIBA Plan of Work splits a construction or fit-out project into numbered stages, from the first business case to the building in use. When a consultant says a design is "at RIBA Stage 3", they are telling you how far it has developed. The current edition, published in 2020, has eight stages:

Stage

Name

What happens on a fit-out

What you should have at the end

0

Strategic Definition

You decide whether a project is needed at all, for example staying and refurbishing, relocating or consolidating, usually around a lease event

An agreed reason for the project and the outcome it must deliver

1

Preparation and Briefing

The team gathers headcount, ways of working and future growth, surveys the building and reviews the lease

A brief, a budget and a target programme

2

Concept Design

Designers test layouts and space plans, set the look and feel and outline how the building services will work

A signed-off concept design and cost plan

3

Spatial Coordination

The design is coordinated with the building services, structure and fire strategy, and Licence to Alter submissions are often made

A coordinated design that can be priced with confidence

4

Technical Design

Detailed drawings and specifications are produced, building control is engaged and long-lead items are ordered

All the information needed to build

5

Manufacturing and Construction

The contractor takes possession of the site, carries out strip-out, installation and commissioning, and works to Practical Completion

A finished space at Practical Completion

6

Handover

Snags are closed out, O&M manuals and the health and safety file are handed over and the rectification period runs

Defects fixed and the building contract concluded

7

Use

You occupy the space, maintain it and review how well it works for your people

Feedback that shapes the next change to the workplace

You may still see older stage names in some documents. The 2013 edition called Stage 3 "Developed Design" and Stage 5 "Construction", so a reference to "Developed Design" means roughly the same point as today's Spatial Coordination. RIBA also notes that Stages 4 and 5 overlap on most projects, because technical design for some elements continues once work starts on site.

Details and Why It Is Important

RIBA stages give everyone on a project a shared way to describe progress, and they often appear in appointments and fee schedules. Stage 5 starts when the contractor takes possession of the site and finishes at Practical Completion.

The stage also tells you how fixed a design is. Changes at Stage 2 cost little, while changes at Stage 4 mean redrawing coordinated technical information and repricing. If your fit-out is procured design and build, the contract is often signed around Stage 3 or 4, so your brief needs to be settled before then.

Habit Action runs its fit-outs through its own 6D methodology (Discover, Document, Design, Develop, Detail and Deliver) followed by Aftercare. If your consultants report against RIBA stages, ask us how our stages line up with theirs.

In Short

The RIBA stage tells you how far a design has progressed, from Stage 0 to Stage 7. The later the stage, the more a change costs.

Leasing and Landlord Terms

HoTs

What It Stands For

Heads of Terms, sometimes written HOTs or called heads of agreement.

What It Means

Heads of Terms are a short document recording the main commercial points a landlord and tenant have agreed before solicitors draft the lease. They are almost always marked "subject to contract", so they are not legally binding, apart from any clause that expressly says otherwise, such as exclusivity or confidentiality.

Details and Why It Is Important

For a fit-out, the HoTs decide the starting conditions of the whole project. They typically cover:

  • the condition the space is handed over in (shell, Cat A or an existing fit-out)
  • the length of any rent-free period, which is often sized around the fit-out programme
  • any landlord contribution towards the fit-out
  • break clauses and lease length
  • what you must reinstate when you leave
  • the exact scope of work it covers
  • a maximum spend, so costs cannot creep beyond what was approved
  • an expiry date
  • how and when the contractor will be paid
  • which terms apply if the main contract is never signed
  • Minor Works Building Contract for smaller, straightforward works
  • Minor Works Building Contract with contractor's design, where the contractor designs specific parts
  • Intermediate Building Contract for medium-sized works with a fuller design
  • Design and Build Contract where one contractor is responsible for design and construction

In England and Wales, the RICS Code for Leasing Business Premises (2020) sets out what Heads of Terms should cover. Our advice is to get a fit-out contractor to walk the space before you sign. A rent-free period agreed without a realistic programme behind it is the most common way occupiers end up paying rent on a building site.

In Short

HoTs are the agreed outline of a lease deal. They aren't binding, but almost every fit-out dispute about scope, cost or timing traces back to what they said or left out.

LTA

What It Stands For

Licence to Alter.

What It Means

A Licence to Alter is the landlord's formal written consent, usually completed as a deed, for a tenant to carry out specific works to leased premises. It describes the permitted works and the conditions attached to them, and it stays with the lease for its whole term.

Details and Why It Is Important

Most commercial leases say you cannot make alterations without the landlord's consent, and many add that consent cannot be unreasonably withheld. Some ban structural alterations outright. Starting fit-out works without a Licence to Alter is a breach of lease, even when the works themselves are sensible.

The usual process runs like this:

  1. You submit drawings and specifications for the proposed works.
  2. The landlord's surveyor or engineer reviews them, and you normally pay their fees.
  3. Comments go back and forth until the design meets the landlord's building standards.
  4. Solicitors complete the licence.
  5. The works go ahead as agreed, and the landlord may inspect them.

The licence matters beyond the build. It often states which alterations you must remove at the end of the lease, which feeds straight into your dilapidations bill. In a multi-tenant building, the landlord's review also checks how your works affect shared systems such as the fire alarm and HVAC. Build the review period into your programme from day one, because landlord comments can take weeks to come back.

In Short

The LTA is your permission to build. Get it signed before work starts and read its reinstatement clause as carefully as the scope.

Dilaps

What It Stands For

Dilapidations.

What It Means

Dilapidations are the claim a landlord makes at the end of a lease for any breach of the tenant's repair and reinstatement obligations. The claim is set out in a document called a schedule of dilapidations.

Details and Why It Is Important

Dilapidations are where today's fit-out decisions come back as tomorrow's costs. A mezzanine or a new server room may need to be stripped out at the end of the lease if the Licence to Alter says so.

In England and Wales, section 18(1) of the Landlord and Tenant Act 1927 caps damages for disrepair at the loss in value of the landlord's interest. Claims are also expected to follow the Dilapidations Protocol before anyone goes to court. The best protection you have is a photographic schedule of condition agreed at the start of the lease, because you cannot be asked to hand back a building in better condition than you received it, unless the lease says so.

In Short

Dilaps is the exit bill. Plan for it at the start of the lease, and design your fit-out knowing which parts you may have to remove.

Contracts and Procurement Terms

LOI

What It Stands For

Letter of Intent.

What It Means

A Letter of Intent is a letter from a client to a contractor saying they intend to sign a building contract and asking the contractor to start some work before that contract is in place. On a fit-out, it usually covers early design or ordering long-lead items.

Details and Why It Is Important

An LOI has no fixed legal status. Depending on its wording and on how both sides behave afterwards, it can be a non-binding statement of intent or a binding interim contract. In RTS Flexible Systems v Molkerei Alois Müller (2010), the UK Supreme Court found a contract existed on agreed terms even though the documents were marked "subject to contract", because the parties had carried on working as if they had a deal.

That is why a loose LOI is risky for both sides. A good fit-out LOI should set out:

Use an LOI to protect the programme, then get the full contract signed as quickly as you can. An LOI that keeps being extended is a sign the main contract negotiation needs attention.

In Short

An LOI lets a fit-out start before the paperwork is finished. Keep its scope and spend tight, and take legal advice on whether it should bind you.

PCSA

What It Stands For

Pre-Construction Services Agreement.

What It Means

A Pre-Construction Services Agreement is a paid contract that brings a contractor in early to develop the design and price the works before the main building contract is agreed. It is the first stage of what the industry calls two-stage tendering.

Details and Why It Is Important

On complex fit-outs, the contractor's input before the price is fixed is often worth more than a competitive tender on an incomplete design. Laboratories and defence facilities carry specialist services and building constraints that often only show up once someone investigates. A PCSA pays for that investigation upfront, so the price you sign is based on real information.

The agreement should spell out what the contractor delivers during pre-construction, what it costs and what happens if you decide not to proceed. You keep the right to walk away and take the design work elsewhere, provided the PCSA says the design is yours to use.

In Short

A PCSA buys early contractor expertise and a more reliable price. It suits technical and complex fit-outs best.

JCT

What It Stands For

Joint Contracts Tribunal.

What It Means

The Joint Contracts Tribunal is the UK body that publishes standard forms of building contract. When someone says a fit-out is "on a JCT", they mean the contract is one of its published forms, usually with some amendments.

Details and Why It Is Important

The JCT was founded in 1931 by the Royal Institute of British Architects and the National Federation of Building Trades Employers. Its forms are written to balance risk between client and contractor and are familiar to funders and insurers. That familiarity saves time and legal fees.

The current suite is JCT 2024. The Design and Build Contract 2024 was published on 17 April 2024 and the Minor Works family followed on 15 May 2024. The 2024 edition updates the contracts for the Building Safety Act 2022 duty holder regime and allows notices to be given by email.

Fit-outs most often use one of these forms:

Pick the form that matches the size and procurement route of your project, and keep amendments to a minimum. Heavily amended standard forms lose the main advantage of using a standard form at all.

In Short

JCT contracts are the standard rulebook for most UK fit-outs. Check you are on the 2024 edition and that the form fits the project.

D&B

What It Stands For

Design and Build.

What It Means

Design and Build is a procurement route where one contractor is responsible for designing and constructing the fit-out under a single contract. The alternative, often called the traditional route, has you appoint designers first and then tender the finished design to contractors.

Details and Why It Is Important

With design and build, you have a single point of responsibility. If the design and the build don't match up, there is one party to fix it, and design and construction can overlap to shorten the programme. The trade-off is less direct control over detailed design decisions once the contract is signed, so your brief and Employer's Requirements need to be clear.

Under the JCT Design and Build Contract 2024, the contractor's design duty is reasonable skill and care, and fitness for purpose is expressly excluded. If you need a higher standard on a specific element, negotiate it into the contract.

Habit Action delivers fit-outs as a design-and-build contractor, which means the same team that designs your workplace is accountable for building it.

In Short

D&B puts design and construction under one contract and one accountable team. Its success depends on a clear brief at the start.

Space Categories

Cat A

What It Stands For

Category A, also written CAT A. You may also see Cat A+.

What It Means

A Cat A fit-out is the landlord's base level of finish that turns a bare shell and core building into a usable but empty space. Shell and core is the stage before it: the structure, lifts, stairs, toilets and incoming services, with nothing fitted out on the office floors.

Details and Why It Is Important

A typical Cat A space includes raised access floors, suspended ceilings with lighting, finished walls, basic fire detection and heating and cooling distributed for an open-plan layout. It has no meeting rooms or kitchens.

Cat A+ goes a step further, adding furniture and meeting rooms so a tenant can move in with minimal work. It suits small or short-term occupiers who need speed more than a space designed around them.

The catch with Cat A is that it is designed for nobody in particular. If your layout needs cellular offices or a different ceiling, some of the brand new Cat A installation may be ripped out during your own fit-out. Ask the landlord early whether they will offer a contribution or rent-free period instead of completing Cat A works you will undo.

In Short

Cat A is a finished, empty space built to the landlord's standard. Check how much of it your own layout will keep before you agree to pay for it.

Cat B

What It Stands For

Category B, also written CAT B.

What It Means

A Cat B fit-out is the occupier's own fit-out, built on top of Cat A to suit how their business actually works. It turns an empty floor into a working space.

Details and Why It Is Important

Cat B covers everything specific to you. Typical elements include partitions and meeting rooms, kitchens and breakout areas, furniture, IT and AV, brand finishes and any changes to the building services needed for the new layout. On technical spaces, it also includes the specialist installations, such as laboratory extraction or secure areas.

Cat B is where most of the cost sits, and the occupier usually pays for it. It is also the part a landlord will want removed at the end of the lease unless the Licence to Alter says otherwise, so the Cat B design and your dilapidations exposure should be planned together.

In Short

Cat B is your fit-out, designed around your people and processes. It is where the money goes and where the best results come from a clear brief.

Building Services Terms

MEP

What It Stands For

Mechanical, Electrical and Plumbing. Some specifications write M&E (Mechanical and Electrical) instead.

What It Means

MEP is the collective name for the building services that make a space usable. Mechanical covers heating, cooling, ventilation and extraction. Electrical covers power, lighting, fire alarms and data containment, and plumbing covers water supply and drainage.

Details and Why It Is Important

MEP is usually one of the largest cost packages in a fit-out and the one with the longest lead times. It is also the part occupiers see least, because most of it sits above the ceiling or below the floor.

On technical spaces, MEP drives the whole project. A laboratory's extraction or a production line's power supply can decide the layout before any interior design starts. Survey the existing services early, because reusing what is already there is often the biggest saving available.

In Short

MEP is the services that make a building work. Get it surveyed and designed early, especially on technical fit-outs.

HVAC

What It Stands For

Heating, Ventilation and Air Conditioning.

What It Means

HVAC is the group of systems that control temperature and air quality inside a building. It is the largest part of the mechanical side of MEP.

Details and Why It Is Important

In a fit-out, the HVAC design has to work with the plant the building already has, such as chillers and air handling units, while matching a new layout and a new number of people. Adding meeting rooms or increasing desk numbers changes how much fresh air and cooling each area needs.

In England, ventilation is covered by Part F of the Building Regulations and energy efficiency by Part L. Poor HVAC design shows up quickly as stuffy meeting rooms and cold spots, so it deserves proper attention even on office projects.

In Short

HVAC is the climate control of your workplace. A new layout almost always means the HVAC needs adjusting to match.

AHU

What It Stands For

Air Handling Unit.

What It Means

An Air Handling Unit is a large piece of plant that draws in outside air, filters it, heats or cools it and distributes it through ductwork. It is usually the source of the fresh air in a building, often with heat recovery from the air it extracts.

Details and Why It Is Important

The AHU sets a hard limit on how much fresh air your floor can receive. If your fit-out raises occupancy well above what the building was designed for, local units can keep the temperature comfortable, but the fresh air supply may still fall short. Ask for the AHU capacity allocated to your floor before you fix a desk count.

In Short

The AHU supplies a building's fresh air. Its capacity limits how many people your space can comfortably hold.

FCU

What It Stands For

Fan Coil Unit.

What It Means

A Fan Coil Unit is a local unit, usually hidden in the ceiling, that blows room air across a coil to heat or cool one zone. Most office FCUs use chilled water for cooling and low-temperature hot water for heating, supplied from central plant.

Details and Why It Is Important

FCUs are a standard part of many Cat A fit-outs, laid out for open-plan space. They recirculate and condition room air but do not supply fresh air themselves, which comes from the AHU.

When your fit-out adds partitions, existing FCUs often need moving or extra units adding so each enclosed room has its own control. Replacing FCUs that could be relocated and reused is one of the most common sources of avoidable cost and waste in office fit-outs.

In Short

An FCU heats or cools a single zone. Reuse and relocate existing units where the layout allows.

VRF

What It Stands For

Variable Refrigerant Flow. Daikin's trademarked name for the same technology is VRV (Variable Refrigerant Volume).

What It Means

VRF is a heating and cooling system where one outdoor unit serves many indoor units through refrigerant pipework. It varies the refrigerant flow to each indoor unit, so every zone can run at its own temperature.

Details and Why It Is Important

Daikin introduced the technology in 1982. Heat recovery versions can heat one zone and cool another at the same time, which suits buildings with sunny and shaded sides or mixed uses. Because refrigerant pipework is far smaller than ductwork, VRF suits buildings with limited ceiling space and is common in refurbishments.

There is a design point that catches people out. BS EN 378 limits how much refrigerant can be present relative to the size of an occupied room, so small cellular offices and meeting rooms on a VRF system may need leak detection or a different design. The system also falls under F-gas rules for leak checking and maintenance.

In Short

VRF is a flexible, zoned heating and cooling system run on refrigerant. Check refrigerant limits in small rooms early in the design.

BMS

What It Stands For

Building Management System, sometimes called a BEMS (Building Energy Management System).

What It Means

A Building Management System is the central control system that runs and monitors a building's services, such as HVAC plant and lighting, from one interface.

Details and Why It Is Important

Any new or moved HVAC equipment in a fit-out needs connecting to the BMS so it can be controlled and monitored. In multi-tenant buildings, the BMS usually belongs to the landlord, and the landlord often requires its own controls specialist to make the changes. Include that cost and lead time in your budget and programme.

A well-set-up BMS also gives you data on energy use and comfort after you move in, which helps with running costs and sustainability reporting.

In Short

The BMS is the building's control centre. Every fit-out that touches HVAC also touches the BMS.

Fire Safety Terms

FD Ratings

What It Stands For

Fire Door, followed by the number of minutes the door resists fire: FD30, FD60 or FD120.

What It Means

An FD rating is the British classification for how long a door resists fire, measured on its integrity, meaning how long its structure stops fire passing through. An FD30 door resists the passage of fire for at least 30 minutes, an FD60 for at least 60 minutes and an FD120 for at least 120 minutes. FD doors are tested to BS 476-22.

Details and Why It Is Important

The BS 476-22 test doesn't include smoke. A door marked with an S, as in FD30S, has passed a separate smoke test as well, so check for the S wherever your fire strategy calls for smoke control.

Which doors need which rating is set by the building's fire strategy and Approved Document B. The rating belongs to the whole tested doorset, including the frame, seals and ironmongery, so swapping components without the right certification can invalidate it.

FD ratings are also being phased out. Under changes to Approved Document B in England, BS 476 classifications can only be used until 2 September 2029, after which fire doors must carry a European classification. If your fit-out doors are likely to be replaced or added to before then, specifying E or EI classes now saves re-specifying later.

In Short

FD30, FD60 and FD120 tell you how many minutes a fire door resists fire. The British FD system ends in September 2029.

E Ratings

What It Stands For

E stands for Integrity, followed by the number of minutes: E30, E60 or E120.

What It Means

An E rating shows how many minutes a doorset or assembly resists the passage of fire, measured on integrity alone. E rated doors are tested to BS EN 1634-1 and classified under BS EN 13501-2, the European standard.

Details and Why It Is Important

An E rating has no insulation requirement, so it does not limit how hot the side away from the fire gets. Use it where the fire strategy needs integrity only.

Like the British test, BS EN 1634-1 doesn't include smoke, so a door needs further testing to show smoke resistance. Because E ratings are European classifications, they will remain valid after the British FD system is withdrawn in 2029.

In Short

E30, E60 and E120 are the European integrity-only fire ratings. Smoke resistance needs a separate test.

EI Ratings

What It Stands For

EI stands for Integrity and Insulation, followed by the number of minutes: EI30, EI60 or EI120.

What It Means

An EI rating shows how many minutes a doorset or assembly resists fire on both integrity and insulation. Insulation means the door also limits the temperature rise on the side away from the fire. EI rated doors are tested to BS EN 1634-1 and classified under BS EN 13501-2.

Details and Why It Is Important

EI doors are specified where the fire strategy needs to stop heat building up on the protected side as well as stopping flames. As with E ratings, the fire test doesn't include smoke, so smoke resistance needs further testing.

When you compare quotes, check each product against the exact class in your fire strategy. An E30 door does not meet an EI30 requirement, even though the numbers match. The same classes are used for fire-rated partitions and glazed screens, which are common in fit-outs.

In Short

EI30, EI60 and EI120 cover integrity and insulation. Check whether your fire strategy asks for E or EI before choosing doors.

Site, Safety and Handover Terms

CDM

What It Stands For

Construction (Design and Management) Regulations 2015, usually shortened to CDM or CDM 2015.

What It Means

CDM 2015 is the main UK law on managing health and safety in construction projects, and it applies to fit-outs of every size. It sets out who is responsible for safety at each stage, from design through to handover.

Details and Why It Is Important

CDM gives the client legal duties as well as the contractor. As the client, you must make sure suitable arrangements are in place and appoint a principal designer and a principal contractor in writing whenever more than one contractor will work on the project.

A project must also be notified to the Health and Safety Executive if the construction work will last more than 30 working days with more than 20 workers on site at the same time, or exceed 500 person-days. At the end, you receive a health and safety file, which you keep for future works on the building.

In a design-and-build fit-out, the contractor commonly takes on both the principal designer and principal contractor roles, which keeps responsibility in one place.

In Short

CDM 2015 is the safety law for construction, and clients have duties under it too. Make sure the principal roles are appointed in writing before work starts.

FF&E

What It Stands For

Furniture, Fixtures and Equipment.

What It Means

FF&E covers the items that complete a space but aren't part of the building fabric or services, such as desks, chairs, storage, soft seating, kitchen appliances and signage.

Details and Why It Is Important

FF&E often has some of the longest lead times on a fit-out, especially for specified furniture made to order. If it is ordered late, you can end up with a finished space and nothing to sit on. Decide early whether FF&E sits in your fit-out contractor's scope or with a separate furniture supplier, because a split scope needs someone managing deliveries and installation around the build.

In Short

FF&E is everything you furnish the space with. Order it early and agree who manages it.

PC

What It Stands For

Practical Completion.

What It Means

Practical Completion is the point at which the fit-out is finished, apart from minor defects, and the space can be handed over and used for its intended purpose. On a JCT contract, it is confirmed by a statement or certificate.

Details and Why It Is Important

Practical Completion is one of the most important dates in a fit-out contract because several things change on that day. Responsibility for the space and its insurance passes back to you, any delay damages stop running, half of the retention money is normally released and the rectification period begins.

The rectification period, sometimes called the defects liability period, is when the contractor must return to fix defects that appear. It is commonly 12 months, and if no period is stated, JCT forms default to six months. A snagging list of minor items to finish is agreed around Practical Completion.

In Short

PC is handover day in contract terms. Know what it triggers and agree the snagging list before you sign it off.

O&M

What It Stands For

Operation and Maintenance, as in O&M manuals.

What It Means

O&M manuals are the handover documents that explain how to operate and maintain everything installed in your fit-out. They typically include as-built drawings, product information, warranties, test certificates and maintenance schedules.

Details and Why It Is Important

Without complete O&M manuals, your facilities team or service contractors are guessing how the building works. Warranties can be voided if equipment isn't maintained as the manufacturer requires, and test certificates for electrical and fire systems are what your insurer and the landlord will ask to see.

Ask for the O&M manuals to be delivered at Practical Completion rather than weeks later, and check they cover every system that was installed or changed.

In Short

O&M manuals are the instruction book for your new workplace. Make their delivery part of handover.

SKA

What It Stands For

SKA rating. SKA is a name rather than an acronym, though it is always written in capitals.

What It Means

SKA is an environmental assessment method designed specifically for fit-out projects, run by RICS (the Royal Institution of Chartered Surveyors). Projects are rated Bronze, Silver or Gold against good-practice measures covering energy, water, materials, waste and wellbeing.

Details and Why It Is Important

Whole-building schemes such as BREEAM are aimed mainly at new buildings and major refurbishments, so they fit poorly on a fit-out, where many sustainability decisions sit in the occupier's control. SKA only assesses the measures relevant to the works you are actually doing, which makes it a practical way to set and prove sustainability targets for a fit-out.

If your business reports on environmental performance, or your landlord has targets for the building, agree a SKA target at brief stage. Adding it after the design is fixed is far harder.

In Short

SKA is the sustainability rating built for fit-outs. Set the target at the start of the project.

Fit-Out Jargon FAQs

What is the difference between Cat A and Cat B fit-out?

Cat A is the landlord's base fit-out, a finished but empty space with floors, ceilings, lighting and services. Cat B is the occupier's own fit-out on top of it, adding the layout, furniture and finishes that make it a working space.

Do I need a Licence to Alter for an office fit-out?

In most cases, yes. Most commercial leases require the landlord's written consent before any alterations, and a Licence to Alter is how that consent is formally given and recorded.

Is a Letter of Intent legally binding?

It can be. A Letter of Intent can be non-binding or a binding interim contract, depending on its wording and how both parties act after it is issued, so it should always be reviewed by a solicitor.

What does MEP mean in a fit-out?

MEP stands for Mechanical, Electrical and Plumbing. It covers the building services that make a space usable, including heating, ventilation, power, lighting and water.

Which JCT contract is used for fit-out projects?

There is no single fit-out form. Smaller fit-outs often use the JCT Minor Works Building Contract, while larger ones commonly use the JCT Design and Build Contract or the Intermediate Building Contract, all now on the 2024 edition.

Talk to Habit Action About Your Fit-Out

If your lease or fit-out contract is full of terms like these, our team can walk you through what they mean for your programme and budget before you commit.

Sources

What is the difference between FD and EI fire rated doors? (Selo)

JCT announces release of 2024 Edition of contracts (Clyde & Co)

What's in store from JCT 2024? (Estates Gazette)

What's new in the JCT 2024 Design and Build contract? (RICS)

RIBA Plan of Work 2020 Overview (RIBA)