Skip to content
All posts

£45m MoD Factory Grants: What Defence Manufacturers Should Plan Before They Apply

The Ministry of Defence (MoD) has opened its first capital grants window for new energetics factories, offering UK-based companies up to £45 million each, and applications close at 5pm on 8 January 2027. That gives defence manufacturers about six weeks, with Christmas in the middle, to turn a site idea into a costed project the MoD will believe can be built.

Habit Action’s advice is to settle the site, the power supply and a defensible cost range before anyone starts writing the bid. Assessors will score deliverability alongside military need, and a strong case on paper falls apart if the building behind it is still a guess.

What the MoD Energetics Grant Covers

The grants fund new UK factories that produce explosives, propellants and other energetic materials for the Armed Forces’ munitions. They sit inside the government’s £1.5 billion pledge for an “always on” munitions pipeline, which aims for at least six new energetics and munitions factories and more than 1,000 skilled jobs.

Detail

What the MoD has said

Maximum grant

Up to £45 million per facility, or 50% of eligible capital expenditure if that is lower

First window closes

5pm GMT, 8 January 2027

Later windows

Two more expected in 2027

Who can apply

Any organisation able to deliver energetics manufacturing in the UK, whether or not it took part in the 24 feasibility studies

The 50% cap is the figure most bids will hinge on. You will need to show where the other half of the capital comes from, and private investors will want the same cost certainty the MoD does.

Applications must show the project is militarily useful, technically feasible, commercially viable and deliverable. They also need to meet environmental, regulatory and safety requirements and run on a sustainable long-term basis.

BK5I8211-HDR

What to Plan Before You Apply

Securing a Site That Can Be Licensed

Manufacturing explosives needs a licence from the Health and Safety Executive (HSE) under the Explosives Regulations 2014, and the licence depends on separation distances from neighbouring buildings and roads. Sites holding larger quantities may also come under the Control of Major Accident Hazards (COMAH) Regulations 2015. Speak to HSE and the local planning authority before you commit to a site in the bid, because a site that can’t be licensed sinks the whole application.

Confirming Power and Utilities Early

Process plant and its ventilation draw heavily on power, and a new grid connection is often the longest lead item on a factory programme. Ask the network operator for available capacity now and put the answer in the bid. On Isembard’s 38,000 sq ft global HQ in London, Habit Action increased the electrical infrastructure for CNC machinery as part of a 12-week design and build.

Building a Programme the Assessors Will Believe

A deliverable programme shows every consent and long-lead item with a date that genuinely allows for it. Security belongs in it from day one. Access control and secure storage shape the layout, so retrofitting them later costs time you won’t have.

Getting to a Cost Range You Can Defend

With the MoD funding half at most, investors and assessors will both test your numbers. Habit Action’s 6D methodology (Discover, Document, Design, Develop, Detail, Deliver) starts with a block plan and a cost estimate accurate to ±20% at Discover, and that range tightens at each stage until it becomes a fixed lump sum at Detail. A Discover-stage estimate is enough to anchor a grant bid and shows the MoD the figure came from a real plan.

Planning the Buildings Around the Process Plant

The energetics process line is specialist chemical engineering, and your process engineers will lead it. Every energetics factory also needs offices, quality-control laboratories, secure stores, welfare facilities and training rooms, and these sit on the same programme and the same budget line in your bid.

Habit Action is a UK design-and-build fit-out company that delivers these spaces for defence and advanced manufacturing clients, with Security Check (SC) cleared personnel available and an approach informed by National Protective Security Authority (NPSA) guidance. Isembard, which manufactures for rockets, drones, nuclear energy and Formula 1, moved into a Habit Action-built HQ with upgraded access control and security. We have also delivered projects in aerospace, the arms industry, defence manufacturing and industrials.

If you plan to apply in this window, book a Discover session with us before the Christmas break. You will leave it with a block plan for the supporting buildings and a cost range to put in front of the MoD and your investors.

HabitAction_LaurelleLondon_LargeFiles_79

Quick Answers on the MoD Energetics Grants

How much can a company get from the MoD energetics grant?

Up to £45 million per facility, limited to 50% of eligible capital expenditure where that is lower.

When does the first application window close?

The first window closes at 5pm GMT on 8 January 2027. The MoD expects two further windows in 2027.

Do you need to have done an MoD feasibility study to apply?

No. The competition is open to any organisation that can deliver energetics manufacturing in the UK, whether or not it took part in earlier feasibility or engineering design work.

Can the grant pay for offices and laboratories on an energetics site?

Check the definition of eligible capital expenditure in the grant notice on Find a Grant. Either way, those buildings belong in your programme and cost plan, because assessors judge whether the whole facility can be delivered.

Sources