Defence companies can expand manufacturing facilities while keeping production running by mapping what can't stop, phasing works around live and secure areas, and planning the return to production before work starts. At Isembard, Habit Action delivered a 38,000 sq ft London headquarters, including increased electrical capacity for CNC machinery, in an accelerated 12-week programme.

Key Takeaways

  • Start with the production bottleneck, not the square footage: power, logistics, storage or layout can all limit output more than floor space.
  • List the 11 things that can't simply be switched off, from production lines to fire and life-safety systems, before anyone draws a phasing plan.
  • Phase the works so new capacity comes online in stages; at Sigma Pharmaceuticals, a mezzanine doubled the existing warehouse floor area and freed space around production.
  • On defence sites, every phase must keep secure areas protected, with access control and segregation in place from day one of the works.
  • Plan commissioning, validation and production trials before construction starts, so finished works don't sit idle waiting for sign-off.

How can defence and advanced manufacturers expand without stopping production?

For an advanced manufacturing organisation, expansion is only successful if production can continue while the building changes around it.

A larger facility doesn't automatically mean greater output. If production slows, teams can lose access to essential equipment, logistics can become harder to manage and critical utilities can be disrupted. In some cases, the expansion can even create new operational problems.

The key is to design the expansion around the production requirement, rather than simply designing a bigger building.

For manufacturers operating in defence, aerospace, automotive and elite engineering, this means understanding:

    • How the facility works today
    • Where the bottlenecks are
    • What needs to remain operational throughout the project
    • What the operation will need as production grows

Here are five ways to minimise downtime during an advanced manufacturing expansion.

Warehouse for Clarity Pharma, delivered by Habit Action

1. What should you plan before expanding a manufacturing facility?

Plan around what's limiting production today and what the operation will need in two, five and ten years, then design the building to suit.

Start with the production requirement, not the building. Before deciding what to build, understand what is actually limiting production today, what the organisation needs to achieve and how those requirements are likely to change.

When an organisation needs more production capacity, the natural response is often to look for more space. But square footage is only part of the answer.

Where is the bottleneck?

Is it:

    • Available production space?
    • Material movement?
    • Storage capacity?
    • Specialist equipment?
    • Power or other utilities?
    • Loading and logistics?
    • Workforce capacity?
    • Testing or inspection space?
    • The layout of the existing facility?

This creates a much more useful starting point than simply deciding how many additional square metres are required.

It is also important to look beyond today's requirements. What will production look like in two, five or ten years?

If demand is expected to increase significantly, the facility may need additional electrical capacity, stronger floors, more services, automation infrastructure, improved logistics or space that can be adapted as production changes.

 

The best expansion strategy therefore starts with a simple question: What does production need the building to do?

Only then should the building be designed around those requirements.

Habit Action in practice: Isembard

At Isembard, the brief wasn't simply a bigger workplace. Habit Action delivered Isembard's new 38,000 sq ft London headquarters, which needed increased electrical capacity for CNC machinery, infrastructure for automation and improved production processes. The project ran on an accelerated 12-week programme, so design and delivery decisions had to be driven by operational requirements from the first day, not tidied up at the end. Power, equipment, automation, logistics and future flexibility were all part of the expansion strategy. The lesson: manufacturing capacity depends on far more than floor space. A big empty shed with not enough power is nobody's idea of progress.

Warehouse for Isembard delivered by Habit Action

2. What has to keep running during a manufacturing expansion?

Anything that can't simply be switched off: production equipment, utilities, logistics routes, testing areas, secure spaces and safety systems.

Before construction begins, identify everything that cannot simply be switched off. This includes production equipment, utilities, logistics routes, testing areas, secure spaces and the systems that allow people and products to move safely through the facility.

An advanced manufacturing facility can contain a complex network of activities and infrastructure, including:

    • Production lines
    • Specialist machinery
    • Loading and logistics routes
    • Testing areas
    • Secure areas
    • Staff access
    • Electrical infrastructure
    • Data and communications
    • Compressed air and extraction
    • Fire and life-safety systems
    • Specialist water, drainage or gases

These requirements need to be mapped before construction begins.

This is one of the biggest differences between an ordinary refurbishment and a mission-critical manufacturing project.

You aren't simply asking: “Where can we build?”

You're asking: “Where can we build without affecting production?”

How do you phase works around secure areas on a defence site?

Phase the works so secure areas are never left unprotected: each phase should keep the secure perimeter, access control and intruder detection working, or replace them with agreed temporary measures before anything is removed. On sites handling classified work, such as List X sites (UK commercial sites approved to hold classified government information), the security team should approve the phasing plan before work starts. Agree which contractors need Security Check (SC) clearance, who must be escorted, and how hoarding and segregation will separate construction from secure production. The National Protective Security Authority (NPSA), the UK government's protective security authority, publishes physical security guidance that's a sensible reference, alongside MOD security policy (historically JSP 440) and the client's own security conditions. Confirm what Habit Action holds: clearances, List X experience, secure-site credentials. Nobody wants to explain to their security controller that the fence came down a week before the new one went up.

Isembard Technical facilities delivered by Habit Action

3. How does phased construction keep production running?

Phasing splits the expansion into stages, so new capacity comes online one area at a time while the rest of the facility keeps working.

Phased construction divides an expansion into manageable stages, allowing work to take place around an operating facility. Instead of attempting to complete everything at once, new capacity can be brought online progressively while unaffected areas continue to operate.

For example, an expansion might begin with additional warehouse or storage capacity. Once that area is operational, it can provide temporary capacity while work moves into another part of the facility.

Expansion doesn't always need to start with the production floor.

Habit Action in practice: Sigma Pharmaceuticals

At Sigma Pharmaceuticals, the challenge included an inefficient goods-out facility alongside growing demand. The solution included a new picking system and a mezzanine that doubled the existing warehouse floor area.

Sometimes the quickest way to release production capacity is to improve the space around production.

Production areas can then be expanded in smaller stages, allowing teams and equipment to move between completed and temporary spaces as required.

This creates a rolling programme:

Build → relocate → release space → build again → bring new capacity online.

The principle is simple: don't stop the entire operation when you only need to stop one part of it.

Why does programme speed matter in a manufacturing expansion?

External Facilities for Sigma Pharmaceuticals delivered by Habit Action

Habit Action's work with Isembard demonstrates the importance of aligning programme, infrastructure and manufacturing requirements.

The 38,000 sq ft HQ was delivered in 12 weeks, with the project incorporating increased electrical infrastructure for CNC machinery and infrastructure for automation.

For advanced manufacturers, a faster programme isn't simply about finishing construction sooner. It can mean getting additional manufacturing capability operational sooner.

The right phasing strategy will depend on the operation, but the objective remains the same: keep as much of the production environment operational as possible, for as long as possible.

4. How do you build around a live manufacturing operation?

Plan contractor access, deliveries, routes and isolations around how people, products and services actually move through the building.

The construction methodology needs to work around the way the facility actually operates. Phasing alone isn't enough. The project team needs to understand how people, products, equipment, materials and services move through the building and plan construction around those requirements.

That means considering practical questions early:

    • Where will contractors access the building?
    • How will materials enter the site?
    • Can deliveries continue?
    • Will construction routes cross production routes?
    • What happens if a critical utility needs to be isolated?
    • Where can equipment or staff temporarily relocate?
    • What areas require additional security or segregation?

These decisions can have a significant impact on downtime.

Advanced manufacturing facilities often have highly specialised workflows and complex requirements, so a construction plan that looks efficient on paper can create serious disruption once it interacts with the live operation.

Habit Action in practice: Origin Pharmaceuticals

At Origin Pharmaceuticals, Habit Action had to deliver a 16,000 sq ft project while COVID restrictions limited the number of tradespeople able to work on site.

Rather than allowing those constraints to disrupt the client's production spaces, processes were adapted to keep the project moving around the live operation.

It is a useful reminder that minimising disruption isn't only about the construction programme. It is about adapting the delivery strategy to the operational reality of the client.

This is why early coordination between the client, design team, contractor, facilities team and production teams is so important.

Appian Capital kitchen interior delivered by Habit Action

Habit Action in practice: Essex X-Ray

Essex X-Ray's existing facilities were limiting its potential for expansion, including restricted workspace and inefficient operational flow. Its new 59,000 sq ft headquarters in Braintree was therefore designed around much more than simply providing additional floor space.

A high-capacity warehouse was integrated to improve logistics and inventory management, while specialist X-ray rooms were designed around the controlled conditions required for testing and manufacturing. The facility was also designed with future scalability in mind.

The lesson: when a manufacturing facility is designed around how production actually moves through the building, the result can be greater operational capacity rather than simply more space.

The earlier these constraints are understood, the more options there are for working around them.

Technical Machinery installed for Essex X-Ray by Habit Action

5. How should manufacturers plan the return to production?

Plan it before construction begins, because finished works don't mean production can restart until equipment, utilities and safety systems are commissioned.

Manufacturers should plan the return to production before construction begins. Completing the physical works doesn't necessarily mean production can restart immediately. Equipment, utilities, IT, access control, safety systems and production trials may all need to be tested and commissioned first.

A return-to-production plan might include:

    • Equipment installation and testing
    • Utility commissioning
    • Safety checks
    • Environmental controls
    • IT and data connections
    • Access control
    • Equipment validation
    • Staff movement
    • Cleaning and handover
    • Production trials

The goal is to avoid finishing the physical works only to discover that production cannot yet resume.

A well-planned project therefore considers three stages:

Before: prepare the operation and identify constraints.

During: protect production while construction takes place.

After: bring the new or upgraded facility into operation as quickly and safely as possible.

What should a shutdown and phasing checklist include?

A shutdown and phasing checklist covers what happens before, during and after each phase, and who signs it off. Ops and estates teams will want this pinned to the wall. Probably next to the coffee machine, where everyone actually reads things.

Stage

Check

Typical owner

Before

Map every production line, utility and system that can't be switched off

Operations and facilities

Before

Identify the real bottleneck: space, power, logistics, storage or layout

Operations and design team

Before

Check floor loading and power capacity against the equipment you plan to install

Design team and structural/M&E engineers

Before

Agree the phase sequence and where people and equipment will temporarily relocate

Project team and production managers

Before

Agree shutdown windows with customers and supply chain where output is affected

Operations and commercial

Before

Confirm security requirements, contractor clearances and escort arrangements for secure areas

Security manager

During

Keep contractor routes and deliveries separate from production routes

Contractor

During

Plan and sign off each utility isolation, with a tested reinstatement plan

Contractor and facilities

During

Keep fire and life-safety systems live, or provide agreed temporary cover

Contractor and facilities

During

Maintain secure perimeters, access control and segregation at every phase

Security manager and contractor

After

Commission utilities, environmental controls, IT and access control

Contractor and specialists

After

Install, test and validate equipment, then run production trials

Operations and quality

After

Clean, hand over and release the next area for the next phase

Project team

What's the best way to minimise downtime during an expansion?

Make production continuity part of the brief from day one, not something the contractor works out on site.

The most effective approach is to treat production continuity as a design requirement, not a construction afterthought.

That means understanding how the facility operates before work begins, identifying what cannot be interrupted, and developing the construction programme around those requirements.

For defence manufacturers, this can be particularly important. Growth may be driven by new contracts and increased demand, meaning additional manufacturing capacity needs to come online without compromising the production already supporting existing programmes.

Clarity Pharma technical warehouse delivered by Habit Action

A production interruption can affect delivery schedules, customer commitments, workforce productivity and the ability to manufacture critical products.

The facility therefore needs to support today's manufacturing requirements while creating the infrastructure to respond to future demand.

At Habit Action, we approach advanced manufacturing projects from that operational perspective, considering production, utilities, logistics, security, specialist requirements and future growth alongside the physical space.

The best expansion isn't the biggest one. It's the one the production line barely noticed until the new machines turned up.

Planning an expansion around live production? Our Manufacturing Fit-Out Readiness Assessment helps you identify the risks to address first. Or speak to our team about phasing works around a live, or secure, operation.

FAQs

How can manufacturers expand without stopping production?

Manufacturers can expand without stopping production by using phased construction, temporary relocation and controlled shutdowns. Work can be completed in one area while unaffected parts of the facility continue operating, allowing new capacity to come online progressively.

What is phased construction in manufacturing?

Phased construction divides a manufacturing expansion into smaller stages so that construction can take place around an operating facility. Areas can be completed, commissioned and brought into use before work moves to the next phase, reducing the need for a single large shutdown.

How do you minimise downtime during a factory refurbishment?

Start by identifying which production activities, equipment and utilities cannot be interrupted. The refurbishment programme can then be designed around these requirements, using phased works, temporary arrangements and planned shutdown windows to protect production.

What should be considered when expanding an advanced manufacturing facility?

Consider production flow, available space, power capacity, equipment, floor loading, logistics, specialist utilities, security, testing requirements and future growth. The facility should be designed around how the manufacturing operation works rather than simply how much additional floor space is required.

How long should a manufacturing shutdown last?

There is no standard shutdown period for an advanced manufacturing facility. The objective should be to make shutdowns as short and controlled as possible by planning isolations, equipment moves, installation, commissioning and production restart in advance.